Consider the following project.
Activity Duration (weeks) Precedence Relationship
1 2 -
2 1 -
3 3 -
4 2 1, 2
5 3 2, 3
6 3 4, 5
7 1 -
8 2 6, 7
9 1 7
10 1 8, 9
a) Draw the project network.
b) Determine the slack for each activity
c) Identify the critical activities.
d) What is the least number of weeks required to complete the project?