Question: A critical communications relay has constant failure rate of 0.01 per day.Once it has failed ,the mean time to repair is 2.5 days (repair rate is constant).
(a) compute the steady state availability,
(b) Compute the interval availability over a 2 days mission ( starting at time zero),
(c) what is the point availability at the end of the 2 days.