Question: 1. A construction project has the following network and activity times:
a. Make a forward pass and a backward pass on the activity times.
b. Find the slack for each activity.
c. Prepare a Gantt chart for this project.
d. Activity D will be delayed by one day. What effect will this have on the project?
2. A plant start-up is based on the following network
a. Draw a network for this project.
b. What is the project completion time?
c. Identify the critical path.