A constant current of 3 a for 4 hours is required to charge


A constant current of 3 A for 4 hours is required to charge an automotive battery. If the terminal voltage is 10+ t/2 ,where t is in hours,

a) How much charge is transported as a result of the charging?

b) How much energy is expanded?

c) How much does the charging cost? Assume electricity cost 9cents/kWH.