A conditioned space has a latent load of 12,000 Btu/hr and a sensible load of 20,000 Btu/hr. The space is to be maintained at 75 deg F, 40% rh. Determine the required flow rate of air through the chiller in CFM, and the humidity ratio of the supply air if it is to be delivered at 60 deg F.