A company working on a 75 percent learning curve has


A company working on a 75 percent learning curve has decided that the production standard should be 86 hours of production for the 100th unit. how much time should be required for the first time? If the first unit requires more hours than you anticipated, does this mean that the learning curve is wrong?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A company working on a 75 percent learning curve has
Reference No:- TGS01101979

Expected delivery within 24 Hours