A company uses a Kanban system in the production facility for the jitterburg car the facility operates 8 hours per day. A certain part requires 150 seconds of processing at machine A and a container of parts average 1,6 hours of waiting time there. Management allows a 10% buffer for unxpected occurrences
Each container hold 30 parts and 8 containers are authorised. How much daily demand can be satisfied with this system?