A company operates a line that produces self-adhesive tiles


A company operates a line that produces self-adhesive tiles. The production line of a company consists of single-machine stations and is almost balanced (i.e., station rates are nearly equal). A company engineer has estimated the bottleneck rate to be 2200 cases per 16-hour day and the raw process time to be 30 minutes. The line has averaged 1,500 cases per day, and cycle time has averaged 5 hours.

What is the estimated average WIP level? also show calculations 

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: A company operates a line that produces self-adhesive tiles
Reference No:- TGS01119323

Expected delivery within 24 Hours