A company manufactures a chemical, Dynamite, using two compounds Flash and Bang. The standard materials usage and cost of one unit of Dynamite are as follows.
|
$
|
Flash
|
5 kg at $2 per kg
|
10
|
Bang
|
10 kg at $3 per kg
|
30
|
|
|
40
|
In a particular period, 80 units of Dynamite were produced from 500 kg of Flash and 730 kg of Bang.
Required
Calculate the materials usage, mix and yield variances.