1. Which of the following statements is best?
1) using a non-bottleneck 100% of the time produces 100% utilization
2) time saved at a non-bottleneck saves nothing
3) the capacity of a system depends on the capacity of the bottleneck
4) a and b only are true
5) b and c only are true
2. A bill of material whose purpose is to simplify forecasting, master production scheduling and material requirements planning is called:
1) a summarized parts list
2) where-used bill
3) planning bill
4) structured bill
5) multi-purpose bill