(a). A program in the Engineering and Manufacturing Development (EMD) phase has just been instructed to add some new electronic "black boxes" to the aircraft. The Program Executive Office needs a quick estimate of the cost impact these new additions that is as accurate as possible. The Program Office has access to a database of the costs of adding similar equipment to 15 other types of aircraft. What is the most appropriate cost estimating method for this situation?

Analogy

Engineering

Actual Cost 

Parametric

(b) 

Which one of the following best describes DoD philosophy of budgeting for a Fixed Price - Economic Price Adjustment contract?

 Budget for the anticipated final negotiated price

 Budget for the ceiling price

 Budget for the target price

 Budget for the estimated negotiated price and the maximum amount of the price adjustment clause

Request for Solution File

Ask an Expert for Answer!!
Cost Accounting: a a program in the engineering and manufacturing
Reference No:- TGS0498023

Expected delivery within 24 Hours