A 5 year project has an initial fixed investment of 335,000, an initial NWC investment of 35,000 and an annual OCF of -34,000. The fixed asset is fully depreciated over the life of the project and has no salvage value. If the required return is 10%, what is this projects equivalent annual cost (EAC)?