A 3m deep layer of clay is underlain by impervious rock. An extensive area of fill is to be placed over the site.
How long would it take for the clay layer to achieve 90% of its total final settlement?

Note: that a 20mm high sample of clay achieved 50% of its total final settlement in a standard oedometer test in 4.2 min.