1example please remove before completing document critical


1 Example: please remove before completing document. Critical equipment does not arrive on time. If critical pieces of equipment do not arrive on time, the project will fall behind schedule. H H Red Negative 1. Add activities to the WBS to ensure with the manufacturer that the equipment is being built or shipped as required. 2. Have a member of project team go to the manufacturing plant to ensure equipment parts are in progress and on schedule. 3. Add steps to the WBS to ensure the manufacturer ships on time. 4. Add steps to WBS to track the shipment as needed. Parts do not ship on assigned date. If possible, have a backup supplier identified and standing by. 

Request for Solution File

Ask an Expert for Answer!!
Business Management: 1example please remove before completing document critical
Reference No:- TGS0999293

Expected delivery within 24 Hours