1.A well-thought out SOW should include a list of Work Packages and Activities required to deliver the project.
True
False
2.Corporation's use of project management has expanded dramatically in the last several years. Some of the reasons include _____________ (select 2 best answers)
a.Increased profits available to spend on projects
b.Corporate Downsizing: project management is replacing middle management to get work done
c.Time to market: more cross-functional project teams to speed product development and delivery
d.Increase in number of credentialed project managers to lead projects
3.If a customer tells you that all 2010 tax changes must be implemented in the new system no later than January 1, 2010, then schedule is ___________ (Select the 1 best answer)
pre-determined
really tight
Customer-driven
constrained
4.Qualities of a well-defined work package include (Select the 2 best answers):
a.lowest level of de-composition in the work breakdown structure
b.can be completed by a single resource
c.does not need to include a WBS code
d.cost and duration can be reliably estimated
5.The purpose of Project Scope Management is to _____________ (Select the 1 best answer)
Define the specifications and functionality of the deliverable
Organize the project into phases
Create- a WBS
Define and control what is and what is not included in the project