10. Which of the following is NOT associated with the spreadsheet model used to solve the crashing problem? a) Minimize the total cost of completing the project. b) Minimize the number of activities crashed. c) Complete the project by a specified time. d) Maintain the precedence relationships specified in the network diagram. e) Bounds on the amount each task can be crashed.