1. Using the 50-50 Rule, what is earned value for this project?
2. Using the 0-100 Rule, what is earned value for this project?
Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.
|
Budget
|
Begun?
|
Complete?
|
Actual cost
|
Earned Value
|
Task A
|
3,100
|
Yes
|
Yes
|
3,100
|
|
Task B
|
4,000
|
Yes
|
Yes
|
4,500
|
|
Task C
|
2,500
|
Yes
|
Yes
|
2,250
|
|
Task D
|
4,000
|
Yes
|
No
|
3,500
|
|
Task E
|
3,500
|
Yes
|
Yes
|
4,000
|
|
Task F
|
2,500
|
No
|
No
|
0
|
|