1. It cost a contractor $9,765 to manufacture their first unit. The company expects to experience an 82% unit learning curve. Estimate the cost of the 7th unit. (Round intermediate calculations to 4 decimal places)
Possible answers:
- $ 7,615
- $ 8,593
- $ 6,821
- $ 5,594
2. Given the following information, determine the equation for the unit formulation. (Round intermediate calculations to 4 decimal places)
Unit Number (X)
|
Unit Cost (Y) $
|
1
|
800.00
|
2
|
568.00
|
3
|
464.88
|
4
|
403.28
|
Possible answers:
- Y = (800)(X) -0.4941
- Y = (800)(X) -0.1047
- Y = (800)(X) 0.6931
- Y = (800)(X) 0.9300