Kobenhavn Fine Products wishes to balance its line to meet a daily demand of 240 units. Kobenhavn works an eight-hour day on the following tasks:

Task

Time (mins)

Preceding Task

1

0.4

None

2

0.3

1

3

1.1

1

4

0.2

3

5

0.5       

2

6

0.3

3

7

0.6

5

8

0.6

4, 6, 7

1. Find the cycle time, total number of subassemblies required per day, efficiency, and minimum number of stations. Balance the line.

2. Rebalance the line if task 8 requires 0.7 minute.