1 based on the data belowa draw a network diagram


1. Based on the data below:

(a) Draw a network diagram for the project, highlight the  "normal" critical path

(b) Calculate the earliest start and finish times, the latest start and finish times and the slack days for each activity based on normal durations

(c)  If indirect costs of £375 per day could be saved by reducing the overall duration of the project,  what is the minimum cost for the project?

(d) What practical factors should be considered before an activity is crashed?

(e) Describe a practical approach to monitoring the progress of a project like this one.

Activity

Preceded by

Normal days

Crash days

Normal cost (£)

Crash Cost (£)

A

-

4

3

800

900

B

-

6

3

1000

1600

C

-

4

3

900

1200

D

A

5

3

700

1200

E

B,C

4

3

600

750

F

D,E

3

3

400

400

G

F

4

3

800

850

H

F

8

3

1200

3200

I

G,H

9

3

1200

3300

J

H

3

3

600

600

K

J

5

3

2000

2800

L

I,K

7

3

6500

5000

2. Based on the data below calculate the probability that the project will be completed in 20 days or less and discuss the practical considerations that would be relevant if a company doing this project faced a penalty for completion in more than 20 days. What action could be taken to improve the chances of completion within a  20 day period?

Activity

Preceded by

Optimistic days

Most likely days

Pessimistic days

A

-

2

3

4

B

-

4

6

8

C

A,B

6

9

12

D

A,B

4

5

12

E

C,D

3

5

7

Request for Solution File

Ask an Expert for Answer!!
Project Management: 1 based on the data belowa draw a network diagram
Reference No:- TGS0503037

Expected delivery within 24 Hours