--%>

Time Estimates for Individual Activities

Time Estimates for Individual Activities:

A) Weighted Average Activity Time, t =  (a + 4m + b)/6

B) Standard deviation of activity times, σt = (b-a)/6

C) Standard deviation of project completion, σT= √ (∑ σt2)

a = optimistic completion time (1 in 100 chance of completing the activity earlier under normal conditions)
m = most likely activity time
b = pessimistic completion time (1 in 100 chance of completing the activity later under normal conditions)
t = weighted average activity time
σt = standard deviation of activity completion
σT = standard deviation of project completion       

   Related Questions in Microeconomics

  • Q : Labor Productivity The American workers

    The American workers tend to be much productive than their counterparts in the South America or Asia in part as they have: (i) Superior natural genetic endowments. (ii) Access to the better sports programming, that promotes the team-work. (iii) More capital to work wi

  • Q : Least likely example of Substitution

    Can someone please help me in finding out the accurate answer from the following question. Assume that the War in Iraq spilled over into another oil exporting countries. When U.S. gasoline prices rose to, state, $10 per gallon, the least likely outcome would be that:

  • Q : Unitarily elastic for all prices and

    On such demand curve for pizza as in below demonstrated graph, there demand is: (w) elastic for all prices and quantities demonstrated. (x) unitarily elastic for all prices and quantities shown. (y) elastic at high prices and inelastic at low prices. (z) inelastic at

  • Q : Increasing supply problem Whenever the

    Whenever the equilibrium in the figure shown move from point a to point b, raised supply has taken only in the market illustrated in: (i) Panel A. (ii) Panel B. (iii) Panel C. (iv) Panel D.

    Q : Total costs by charges

    When LoCalLoCarbo produces the profit-maximizing quantity and charges the profit-maximizing price, in that case its total costs equal the area of the rectangle as: (i) 0P3cq2. (ii) bdP4P1. (iii) 0P4

  • Q : Characteristic of the market system

    Select the right ans wer of the question. Which of the following is not a characteristic of the market system? A) private property. B) freedom of enterprise. C) government ownership of the major industries. D) competition in product and resource markets.

  • Q : Price elasticity of demand when price

    The Hobbit family buys 72 vegetarian specials yearly at a price of $3.00 each but would consume 192 yearly when the price dropped to $2.40. Therefore their price elasticity of demand is: (w) 4.09. (x) 2.05. (y) 6.15. (z) 0.26.

    Q : Bonds and Market Interest Rates

    Increases within market interest rates are probably to be related with: (1) people’s increasing desires for vast “nest eggs” for security while they retire. (2) bursting a speculative bubble into prices for hi-tech stocks. (3) increa

  • Q : Determine average production cost by an

    When Robomatic Corporation maximizes profit in its production of RoboMaids, its average production cost per robot will be roughly: (1) $3,000 per robot. (2) $5,000 per robot. (3) $7,000 per robot. (4) $9,000 per robot. (5) $11,000 per robot.

  • Q : Sufficient general theory of oligopoly

    A sufficient general theory of oligopoly would: (w) merely blend elements from competitive and monopolistic models. (x) qualitatively account for interdependence in decision making in broad terms. (y) closely fit all types of oligopoly markets. (z) de